Installation of the Bearspaw South feeder main replacement is complete and connected to the water system, and now the City of Calgary will begin the process of commissioning the new line.
Chief Operating Officer Michael Thompson said that work had concluded on the roughly 6.5-kilometre section of pipe, slightly ahead of schedule.
About 2/3 of the project was done through a microtunneling process from the Shaganappi Pump Station to 73 Street NW, while the remaining third was an open cut process along 34 Avenue NW between 73 Street and 89 Street.
“All of the pipe is in the ground. The new Bearspaw South feeder main is now fully built and connected to our water system,” Thompson said.
“This is a huge moment for this project, which started less than 11 months ago, a tremendous amount of work and water savings have brought us to this point.
It doesn’t quite yet mean that Stage Four outdoor water restrictions are done, but there’s light at the end of the tunnel, and the conservation measures could end in a week.
To do this, the old Bearspaw pipe will have to be refilled. Thompson estimated it could take about five days to add 22 million litres of water.
“We’re going to refill it slowly and carefully, with constant monitoring, like we’ve done in the past,” Thompson said.
“We know the old pipe is in poor condition, and it’s still at risk of a break until the new feeder main is in service later in December.”
After it’s filled, the water will need to be tested. If it passes standards, valves will be turned on to help fill the system.
“If all of those steps go well, we expect to be able to lift water restrictions late next week,” Thompson said.
Mayor Jeromy Farkas was elated by news of the pipe’s completion.
“On January 7, I stood before Calgarians and promised that we would move heaven and earth to get this done. I described this as our city’s, our generation’s moonshot. We set an ambitious deadline. We promised that this would be done by the end of the year,” he said.
“We challenged conventional timelines. We asked everyone involved to think differently about how we deliver major infrastructure. And by the end of this year, we’ve landed on the moon, and now we’ve got to bring it home.”
Costs to be tallied when project is wrapped: Thompson
The budgeted project cost was $381 million, according to Thompson. He said they remained on time and on budget.
“We will be, once the project is wrapped up and the bills coming in, we’ll let Calgarians know what the total cost of the project is,” Thompson said.
“But I’m happy to say, as we’ve been working through the project, we have been on budget, we’ve been on schedule, and we’ve been delivering a great quality project.”
Mayor Farkas said that it’s typical for the City of Calgary to audit major projects once they’re complete and he expects that to happen for this Bearspaw feeder main replacement.
“I fully expect that not just as a part of the standard audit process that the City of Calgary conducts for all areas of operation, but also compliance with our independent panel report, the oversight of our new water utility oversight board, and potentially any regulations that might be coming from our provincial government,” the mayor said.
Once the new pipe is commissioned, Thompson said they’ll look at what to do with the old pipe. He said they’ve been looking at different options for lining the pipe so it can remain as a water system redundancy.
“We’ve actually just stepped back from doing that work while we’ve been focused on getting this new Bears Paw South Street domain completed, so that we can get it in service by the end of this year and not have to rely on that old pipe,” he said.
“Then we’ll be taking a look at that old pipe again.”
The project is still on target for a full opening in December.
During the Stage Four water restrictions as the new pipe was connected, Calgarians and surrounding communities managed to stay under 500 million litres for the entire time.