Scotia Place continues to take shape after busy 2025 construction year

Support LWC on Patreon

If you haven’t strolled down by Stampede Park lately, or caught a glimpse just north of the Scotiabank Saddledome, you may have missed the building rising up to join Calgary’s downtown.

Scotia Place, Calgary’s new events centre, is a hive of activity – even in the cold – as the $1.25 billion arena project enjoyed its first full season of construction in 2025.

While there were some timeline slip-ups early in the project, it’s full steam ahead, as the project has gone from a 35-foot deep hole in the ground back in April, to having concrete forms and steel above the ground right now.

Bob Hunter, Scotia Place project lead, said that most of the big hole is filled now. All the footings and exterior foundation walls have been poured; as have the back-of-house area, the dressing rooms, all the way up to street level.

“Since October, the steel structures are in place, and on the south side, it’s quite high, almost to its final height,” he told LWC.

“They move in sections. The steel guys follow the concrete guys, and we’re going to be finishing the main level, street level concourse over the next couple of months.”

The target opening date is still set for the fall of 2027, and Hunter said that thus far all things point to a successful completion by that time. Today, there are ~330 workers on site. That will balloon to up to 1,200 once the building envelope is complete and work begins in earnest on the interior, Hunter said.

“We’ll then start to enclose it, so the exterior cladding that will obviously enclose the building that will start in the next, I would say, in the spring,” he said.

“We will furiously go around the building and enclose the building so that we can start finishing the interiors.”

Budget intact, upcoming milestones

Bob Hunter, project lead for Scotia Place, at the Saddledome parking lot overlooking work on the new Scotia Place building in April 2025. DARREN KRAUSE / LIVEWIRE CALGARY

The building is expected to seat around 18,500 for hockey games and up to 20,000 for concerts. While there’s always tweaking going on as the project advances, Hunter said that the planned front of house experience – the bowl area, the audio, the video – none of that has changed very much since the project was approved and ground broken in July 2024.

There’s work already happening on some areas of the concourse that are complete, according to Hunter. Mechanical and electrical infrastructure is being put in.

What Calgarians will continue to see is the steel going up, followed by the cladding, and then the roof structure. Then the steel studs and drywall for the interior can start to go in.

“We want to finish the steel. We want to finish the roof and get the whole thing sealed up so that we can do the, I’ll call it the softer work than we’re doing now,” he said.

“So, finishing restaurants, suites, seats, or and all that good stuff that you don’t want to get wet.”

When the project was first started, there were questions around the budget and controls in place to ensure costs didn’t spiral in the wake of ongoing US tariffs. Hunter said that a large portion of the project has already been tendered out and tariff protection was built into the tenders.

“The onus is on the supplier, potential supplier, to accommodate any potential tariffs that they might be levied on,” he said.

“We account for it in the budget. It’s there.”

As far as any potential hiccups that would prevent them from reaching some of the 2026 construction milestones, Hunter said they’re always reviewing potential project risks. There’s nothing they foresee that would significantly impact the timeline for next year.

“We review risks every month. We go through them, and we add them, or we take them off,” he said.

“I would say that there’s nothing that wouldn’t be considered…You’d almost have to be catastrophic… because of the control and discipline that goes into the building.”

Hunter said though they look at drawings and renderings of the new Scotia Place all the time, they shouldn’t be surprised by much as the building takes shape. But they often are.

“If you’re not on site for a few days or a week or so, when you come back, you really notice the changes, and positive changes,” he said.

Liked it? Take a second to support Darren Krause on Patreon!
Become a patron at Patreon!

Trending articles

Walcott: Affordability is no longer a stated priority for Calgary city council

Courtney Walcott

New satellite study shows Calgary’s uneven urban greenery

Sarah Palmer

McLean undecided on potential bid for Calgary-Shaw UCP nomination

Darren Krause

City of Calgary awards millions to fund Indigenous housing

Payton Delisle-Miller

Calgary to co-host 2028 World Cup of Hockey in brand new Scotia Place

Kaiden Brayshaw - Local Journalism Initiative

Latest from LiveWire Calgary

Calgary city council approves $609 million in additional cash for the water system

Darren Krause

New bike shop gears up for Calgary youth

Payton Delisle-Miller

Hundreds of Calgary students benefit from trades pathways as demand continues to grow

Kaiden Brayshaw - Local Journalism Initiative

Calgary couple’s app is helping residents be better with money

Sarah Palmer

MORE RECENT ARTICLES

McLean undecided on potential bid for Calgary-Shaw UCP nomination

Darren Krause

New satellite study shows Calgary’s uneven urban greenery

Sarah Palmer

Hiccup on water heroics OK for one day, city says

Darren Krause

City of Calgary awards millions to fund Indigenous housing

Payton Delisle-Miller